Town Services at a Glance:
July 16, 2018• Syosset•
FORMER SYOSSET LANDFILL
First Operable Unit (OU1) Remediation – [On-site]
Second Operable Unit (OU2) Remediation- [Off-site]
Post-Closure (OU1 and OU2)
DEPARTMENT OF PUBLIC WORKS SITE
(proposed redevelopment)
Although this letter focuses on the remediation testing historically performed, it should also be noted that as part of the physical characteristics of the soil, current subsurface investigation consisted of eighty six (86) borings, 21 percolation tests and 19 cone penetration tests (CPTs). Sixty-one borings were performed at the Cerro site and twenty five borings were performed at the DPW site. Boring and CPT locations were laid out by VHB, the site civil engineer, prior to drilling and shown on the boring location plans. Five test pits were performed at the DPW site to investigate conditions at the former incinerator building, equalization tank and scavenger waste treatment plant. These locations are outside the landfill proper. These Test Pit locations were laid out by MRCE prior to excavation.
The borings were performed by Associated Environmental Services, Ltd. (AES) of Hauppauge, NY from November 3, 2015 through January 20, 2016. All borings were continuously inspected by MRCE Resident Engineer, who prepared field logs. Boring depths ranged from 42 to 117 feet. Continuous samples were taken in the upper 12 feet of each boring. The borings at the DPW site were hand augered to 5 feet depth to clear utilities. Samples were taken every two feet from the hand auger to 5 feet and split spoon samples were taken below that. Below 12 feet, soil samples were taken at about 5 foot intervals, and split-spoon soil samples were obtained. During the investigation, monitoring well piezometers were installed for environmental testing purposes in five completed borings at the Cerro site. Ground water measurements were taken throughout the duration of the boring program.
Additionally, Mueser Rutledge Consulting Engineers (MRCE) performed a geotechnical engineering study, dated November 4, 2015 to evaluate the settlement of the landfill cap due to the proposed park development. The analysis considered a range of consolidation parameters for the landfill material. It is estimated that the primary settlement is expected to be 1.5 inch and may occur within the first two months. The secondary settlement that may occur would happen very slowly (estimated over 30 years). Implications of secondary settlement may be some site pavement and sidewalk cracking, which may require minor repair.
In addition, a geotechnical engineering study, “Infiltration Study”, was prepared by MRCE in May 2015 (and is included in Appendix H of the DEIS) to evaluate the potential for seepage from proposed stormwater management structures to migrate into the adjacent landfill waste below the cap at the existing Syosset landfill. This infiltration study indicated that there would be no impact to the Landfill from anticipated stormwater runoff system from the proposed development. Furthermore, the proposed action includes the continuation of ongoing monitoring activities and maintenance of the Landfill cap, pursuant to the ROD, and activities related to the Cerro Wire Property’s acceptance into the BCP with respect to historic use of the subject property. In addition, the proposed project would be in accordance with the restrictive covenants on the Landfill site to maintain the integrity of the Landfill cap.
CERRO WIRE SITE
There have been multiple investigations and remedial actions completed at the Site. These investigations/remedial actions were completed primarily due to the Site’s inclusion in 1983 on the New York State Registry of Inactive Hazardous Waste Disposal Sites (Registry). The Site was delisted from the Registry in 1994 after utilizing Site-Specific Soil Cleanup Objectives (SSSCOs) for copper, cyanide and zinc that are greater than their respective Part 375 Restricted Residential Soil Cleanup Objectives (RRSCOs). Copies of the reports are provided in The Cerro Remedial Investigation Work Plan, dated September 5, 2017, which is a publicly available document.
In 1986, the Cerro Wire Manufacturing facility terminated operation and began to implement a Decommissioning Program with oversight provided by NYSDEC and the NYSDOH. The Decommissioning Program included the cleaning of equipment and structures with the off-Site transportation and disposal of waste materials and salvageable materials. Notable activities included:
Following completion of the Decommissioning Program, additional environmental investigations and remedial activities were completed at the Site beginning in 1987, as detailed below.
Results of the first round of groundwater sampling indicated that unfiltered samples contained lead, manganese, mercury and iron at concentrations above the Ambient Water Quality Standards and Guidance Values (AWQSGVs). A second round of filtered groundwater samples were collected and all samples were below the AWQSGVs for all metals except iron, which only slightly exceeded. Production well sampling: The two on-Site supply wells were sampled (N-3569 at 198-390 feet; and N-6741 at 373-423 feet).
It was at this point that Remedial Actions commenced at the Site under the direction of NYSDEC and NYSDOH. The below sections describe the remedial actions in detail, as well as subsequent environmental investigations.
The CDM Work Plan notes that four areas were identified that exceeded the 5,200 mg/kg SSSCO for copper (neither cyanide nor zinc were identified at concentrations above their respective SSSCOs). While completing the excavations, NYSDEC identified a fifth area with potential copper contamination above 5,200 mg/kg and requested that this area also be excavated.
The excavations were backfilled with 170 cubic yards of certified clean backfill from Oyster Bay Sand and Gravel.
During the second phase of the remediation, the area was excavated to a depth of three feet and an estimated 575 cubic yards of soil was removed from the rail spur area. A total of 36 soil samples from 13 soil borings located in the rail spur area were collected and analyzed post excavation. Analytical results indicated that post excavation samples did not exceed either the SSSCOs (for copper, cyanide or zinc) or the NYSDEC TAGM 4046 Standards. Waste characterization sampling of the soil pile from the rail spur excavation indicated that the soil was considered hazardous for lead. Approximately 300 cubic yards of the excavated soil was transported and disposed of as a lead hazardous waste.
The clarifier area was also excavated to a depth of three feet and an estimated 235 cubic yards of soil was removed. However, analytical results of the 13 soil samples collected from four borings indicated that additional excavation was required in the southwest portion of the area due to elevated concentrations of SVOCs and copper. The excavation was extended to the southwest to nine feet. Analysis of confirmatory soil samples collected following the additional excavation indicated that concentrations were below the SSSCO for copper and below the NYSDEC TAGM 4046 Standards for SVOCs.
Due to the PCB concentration observed in the rail spur area, NYSDOH requested that additional sampling be conducted along the rail siding. Seventeen soil samples were collected along the rail siding from the 0 to 2-foot depth interval and analytical results indicated that PCBs were not present. The rail spur and clarifier areas were remediated under NYSDEC and NYSDOH oversight.
No.6 fuel oil UST
The no. 6 fuel oil UST was removed along with visibly impacted soil. The excavation measured approximately 20 feet by 40 feet by 18 feet deep. Two grab samples were collected from the bottom of the excavation and one composite sample (consisting of two grab samples) was collected from the sidewall of the excavation. All three samples were analyzed for VOCs and SVOCs. Following sample collection, the excavation was backfilled with clean soil. Analytical results indicated that SVOCs in one of the grab samples from the bottom of the excavation exceeded the NYSDEC Spills Technology and Remediation Series (STARS) Alternative Guidance Values for fuel oil contaminated sites. The sample was reanalyzed using TCLP analysis and no leachable SVOCs were detected.
In June of 2004, a soil boring was advanced to 36 feet bls at the former location of the no. 6 fuel oil UST as required by NYSDEC for vertical delineation of soil impacts. Two samples (UST 20-24 and UST 32-36) were submitted for laboratory analysis of VOCs and SVOCs; neither of which were detected in either sample.
No.2 Fuel oil UST
During excavation of the no. 2 fuel oil UST located near the past water tower, petroleum odors and stained soils were observed. An approximate eight-foot deep “L” shaped area was excavated in the area under the water tower to remove contaminated soil observed during excavation. Two sidewall grab samples and two bottom grab samples were collected from the excavation and analyzed for VOCs and SVOCs. SVOCs were detected at a concentration above STARS guidelines in one of the samples analyzed. The sample was re-analyzed using a TCLP analysis, and no leachable SVOCs were detected.
In August of 2004, the area was excavated to a depth of approximately six feet below the bottom of the former No. 2 Fuel Oil UST and one soil sample was collected for analysis of VOCs and SVOCs. No detections were noted.
The debris within the first building E sump was removed, and a vacuum truck was used to remove approximately 280 gallons of sludge and water from within the sump. The sump itself was removed, and the impacted soils surrounding the sump were excavated. NYSDEC requested additional excavation along the southeast excavation sidewall (estimated at 60 cubic yards), northwest excavation sidewall (estimated at 90-95 cubic yards), and the bottom of the excavation (estimated at 25 cubic yards). A total of 12 endpoint soil samples were collected for laboratory analysis of VOCs, SVOCs, PCBs, Resource Conservation and Recovery Act (RCRA) total metals, total copper and total zinc; all parameters analyzed were below either the SSSCOs (copper, cyanide and zinc) and/or the NYSDEC TAGM 4046 Standards; therefore, no further action was required.
The second building E sump, the sump discovered under building G and the interconnecting trench, were each removed and the surrounding soils were removed in one excavation measuring approximately 70-75 feet by 20-50 feet by 4-5.5 feet deep. A total of seven endpoint soil samples were collected for laboratory analysis of VOCs, SVOCs, PCBs, RCRA total metals, total copper and total zinc; all parameters were below either the SSSCOs (copper, cyanide and zinc) and the NYSDEC TAGM 4046 Standards; therefore, no further action was required. A total of approximately 2,700 cubic yards of soil was removed from both excavations and transported off-Site for disposal as non-hazardous waste.
NAC also collected 123 soil samples from beneath the building slabs, concrete trenches, pits and sumps (once all structures were removed). The samples were analyzed for VOCs, SVOCs, PCBs, RCRA total metals, total copper and total zinc. Results were compared to NYSDEC TAGM 4046 Standard and SSSCOs; results indicated SVOCs were present in concentrations above the guidelines in multiple samples. Based on the analytical results, NYSDEC required hot-spot excavations under buildings B, C, D, F and V.
Area 1
Area 1 was located in the former stormwater discharge basin. The debris and residue was located approximately 10 to 20 feet bls. The final excavation measured approximately 50 feet by 50 feet by 25 feet deep. Approximately 3,300 tons of material and debris were transported off-Site for disposal. Final endpoint samples, analyzed for PP metals and total calcium were reportedly below the SSSCOs (copper, cyanide and zinc) and/or the NYSDEC TAGM 4046 Standards. NYSDEC approved filling and grading the area on February 28, 2005.
Area 2
Area 2 was located in the northern area of the Site. Approximately 3,000 tons of material was removed and transported off-Site from this area. Endpoint samples were analyzed for RCRA metals, total copper, total zinc and total calcium. All endpoint samples were reportedly below the SSSCOs (copper, cyanide and zinc) and/or the NYSDEC TAGM 4046 Standards for all parameters analyzed.
Area 3
Area 3 was located in the southern portion of the Site. Approximately 3,200 tons of material was excavated and transported off-Site from this area. Endpoint samples were analyzed for PP metals and total calcium. All endpoint samples were reportedly below SSSCOs (copper, cyanide and zinc) and/or the NYSDEC TAGM 4046 Standards for all parameters analyzed.
XRF is a technique that is used to rapidly assess the presence and concentrations of metals (e.g., lead, zinc, and copper) in soil, alloys, and other media. When used in the field, the technique involves irradiating a sample with x-rays generated by a field portable XRF unit. Metals within the sample respond to the x-rays by emitting (fluorescing) a spectrum unique to each element. The field portable XRF unit captures the fluorescence and converts the information into estimated concentrations of each metal based on media-specific calibrations. If the XRF data is comparable to laboratory data, then it can be confidently used for initial screening and hot spot delineation followed up by confirmatory laboratory analysis. In total, 363 soil samples were scanned with an XRF analyzer during Roux Associates’ November 2015 soil sampling event in general accordance with the direct intrusive analysis protocol described in USEPA Method 6200 (“Field Portable X-Ray Fluorescence Spectrometry for the Determination of Elemental Concentrations in Soil and Sediment”, Rev. 0, February 2007).
Following well development, the five wells located on-Site and the nine existing wells on the adjacent former Landfill site were gauged on June 28, 2016. The water level was measured between 102 and 108 ft bls. The water level data was used to prepare Site groundwater elevation contour and flow pattern map.
As noted above, previous subsurface environmental investigations and remedial actions completed between 1987 and 2015 included the collection and analysis of more than 750 soil samples from approximately 500 locations.
A Data Usability Summary Report (DUSR) provides a thorough evaluation of the analytical data in order to determine whether or not the data, as presented, meets the site specific criteria for data quality and use. The DUSR is developed from the NYSDEC Analytical Services Protocol (ASP) Category B Data deliverable provided by the laboratory. The data generated by the Roux Associates’ November 2015 soil investigation was produced in accordance with NYSDEC ASP Category B deliverables and was reviewed and validated by an independent party in a DUSR. The data generated by the Roux Associates’ July 2016 groundwater investigation was produced in accordance with NYSDEC ASP Category B deliverables and was reviewed and validated by an independent party in a DUSR.
The Applicant has signed the Agreement and has completed and sent the Citizen Participation Plan to the NYSDEC on November 15, 2016. The Applicant submitted the Remedial Investigation Work Plan was submitted to NYSDEC on February 17, 2017, and the public comment period was open between April 5, 2017 and May 5, 2017. Overall, future activities performed in connection with the BCP (including potential remediation) would be conducted under the oversight of the NYSDEC and the NYSDOH. The BCP mandates that the public is kept informed and is provided with opportunities to comment at various stages of the on the project. Further, the development project will comply with the more stringent soil cleanup objectives used under the current BCP, as compared to previous site-specific risk assessment cleanup goals from 1994.
Last modified: August 25, 2026